Our planned maintenance programme details the building component replacements we intend to carrry out over the next five years.  As we plan ahead we have to make certain assumptions about the quality and condition of our stock.  This changes from year to year and we reassess our programme and re-schedule works as required on an annual basis.

 

Planned Maintenance Programme 2010/11
DescriptionAddressNo of Units
Replacement rainwater goods and fascias               Pather Street / Leighton Street /
East Hamilton Street / Stewarton Street     
72-90 Russell Street
Glasgow Road / Cleland Road
39

10
28
totals for contract 77
Repairs to common pathways and stairsMcInnes Court (LSVT)
Muirhouse (LSVT)
15
24
totals for contract 39
Re-roofing and re-renderingNewmains (LSVT)24
totals for contract 24
Replacement external doorsCharles Street8
totals for contract 8
Replacement sanitarywareStation Road /Caledonian Road12
totals for contract 12
Replacement kitchensCharles Street
2a-6d Russell Street
Harthill
Valley View

 8
14
21
39

totals for contract 82
Replacement boilersCambusnethan Street & ad hoc as required30
totals for contract 30
Replacement extract fans

McInnes Court (LSVT)
Newmains (LSVT)
Valley View

15
24
39
totals for contract 78
Replacement smoke detectors & installation
of carbon monoxide detectors
Shaw Crescent
40-60 Kirk Road
 3
 8
totals for contract 11
Rewiring WorksMcInnes Court (LSVT)15
totals for contract 15
 
 
 